The government has accelerated work on the New Integrated Terminal Building (NITB) at Imphal International Airport, with progress reaching 50%. Officials have set December 31, 2026, as the deadline for completion while pushing for improved regional connectivity.
Read More: Tripura Pearl Project Boosts Rural Women
Key Facts
- Project: New Integrated Terminal Building (NITB)
- Location: Imphal International Airport
- Progress: लगभग 50% completion
- Review Conducted By: Anurag Bajpai
- Target Completion Date: December 31, 2026
- Cargo Terminal Deadline: April 30, 2026
- Key Focus Areas: Terminal, apron, approach road, power and water supply
Project Review and Progress
Anurag Bajpai, Additional Chief Secretary (Transport & TCI), reviewed the progress of the New Integrated Terminal Building at Imphal Airport on Saturday.
The review meeting took place at the Airport Authority of India project office. Officials assessed construction progress on the terminal building, apron, approach road, and utility infrastructure.
Senior officials, including Transport Director Khumanthem Diana Devi and representatives from multiple departments, attended the meeting to ensure coordinated execution.
Work Resumes After Delays
Construction activities have resumed at full pace after facing delays due to conflict-related challenges. As a result, the project has now reached around 50% physical completion.
Officials expressed confidence that steady progress will continue. However, they emphasized strict monitoring to avoid further delays.
Deadline and Instructions Issued
Authorities have directed all agencies to follow the timeline strictly. Specifically, they must complete the terminal building, apron, and utility works by December 31, 2026.
At the same time, officials instructed the Deputy Commissioner and PWD to fast-track the Social Impact Assessment for land acquisition. This step remains crucial for building the approach road connecting the National Highway.
Focus on Regional Connectivity
The Transport Department, along with AAI, discussed plans to expand air connectivity. In addition, they held talks with Alliance Air to start flights on the Imphal–Silchar route at the earliest.
Officials also explored the possibility of connecting Imphal with Dibrugarh. If implemented, this move will significantly improve regional air travel in Northeast India.
Cargo Terminal to Become Operational Soon
Officials inspected the new cargo terminal during the visit. They directed the project agency to install equipment quickly and make the facility operational by April 30, 2026.
Furthermore, the AAI Director must expedite security clearances from BCAS to avoid delays in cargo operations.
Coordination Key to Success
Anurag Bajpai stressed the need for strong coordination among departments. Ultimately, timely execution and teamwork will ensure successful project completion and improved infrastructure.
Q&A Section
Q1: What happened?
Officials reviewed the progress of the Imphal Airport terminal project, which has reached 50% completion.
Q2: Who led the review?
Anurag Bajpai led the review meeting.
Q3: What is the completion deadline?
Authorities have set December 31, 2026, as the target completion date.
Q4: What new routes are planned?
Officials discussed starting Imphal–Silchar flights and exploring Imphal–Dibrugarh connectivity.
Q5: When will the cargo terminal start?
The cargo terminal is expected to become operational by April 30, 2026.
Location Context
Manipur plays a strategic role in Northeast India’s connectivity. Therefore, upgrading Imphal International Airport will boost regional transport, trade, and economic growth.