The Tripura High Court has directed the National Highways and Infrastructure Development Corporation Limited (NHIDCL) to submit its overdue bi-weekly progress report on national highway projects by November 24, 2026. The court observed that the agency had failed to submit the report since October 14 despite an earlier order. The direction came during a hearing on the condition and progress of national highways across Tripura.
Meanwhile, the state government’s Public Works Department (PWD) raised serious concerns over damaged road stretches, delayed repairs, drainage problems and slow contractor performance. The court has asked NHIDCL to examine these concerns and take immediate corrective measures to improve road conditions and commuter safety.
Read More: Ratan Lal Nath Predicts BJP Victory in Tripura 2028
Key Facts About the Tripura High Court Order
- Court: Tripura High Court
- Order date: November 17, 2026
- Next hearing: November 24, 2026
- Case: WP(C)(PIL) No. 06 of 2026
- Agency concerned: National Highways and Infrastructure Development Corporation Limited (NHIDCL)
- Main issue: Delays in national highway projects and deteriorating road conditions
- Pending requirement: Bi-weekly progress report overdue since October 14
- State department: Public Works Department (PWD), National Highways
- Major concern: More than 64 per cent of the Khowai-Srirampur highway stretch was reported to be severely damaged.
Tripura High Court Seeks Explanation Over Delayed NHIDCL Report
A Division Bench comprising Chief Justice M.S. Ramachandra Rao and Justice S. Datta Purkayastha issued the direction on November 17 while hearing a suo motu Public Interest Litigation (PIL).
The case, registered as WP(C)(PIL) No. 06 of 2026, concerns the condition, maintenance and progress of national highway projects in Tripura.
The court noted that NHIDCL had not submitted its required bi-weekly progress report since October 14. Therefore, it directed the agency to file the pending report by November 24 after providing an advance copy to the Advocate General of Tripura.
The bench also instructed NHIDCL to examine the concerns raised by the state government and take appropriate corrective action without further delay.
PWD Highlights Serious Damage and Delays in Highway Projects
During the hearing, Tripura Advocate General SM Chakraborti presented the observations of the Public Works Department’s National Highways division regarding NHIDCL’s second bi-weekly progress report.
The state government broadly supported administrative action against contractors who failed to meet their contractual obligations. These measures included temporary suspension and possible termination of contracts.
However, the PWD highlighted repeated delays in the tendering process. According to the department, single-bidder responses and technical disqualifications had slowed the process of appointing contractors.
The department also expressed concern over extensive damage across several highway stretches. It called for faster execution of permanent repair work instead of relying mainly on temporary solutions.
NH-108B and NH-208 Projects Face Major Challenges
The PWD raised specific concerns about several national highway packages.
1. Package-II: Mohanpur-Subalsingh (NH-108B)
Covering parts of West Tripura and Khowai districts, this stretch has suffered significant structural and drainage damage.
The department stressed that authorities must accelerate permanent repairs instead of depending largely on temporary arrangements involving gravel and boulders.
2. Package-III: Subalsingh-Khowai
For this stretch in Khowai district, the PWD recommended daily monitoring of the contractor’s work.
It also called for immediate contractor replacement if the work failed to meet required road safety standards.
3. Package-IV: Srirampur-Bamanchara (NH-208)
The department sought faster temporary repairs and an early appointment of a new contractor to address the road’s deteriorating condition.
4. Package-V: Khowai-Srirampur
The PWD described this stretch as particularly serious, reporting that more than 64 per cent of the road was severely damaged.
Deep potholes and distorted road surfaces have raised concerns about commuter safety. The department warned that temporary gravel repairs could quickly deteriorate during heavy rainfall.
It also emphasised proper compaction of underlying road layers and functional drainage systems to prevent further damage.
High Court Told to Consider Permanent Road Safety Measures
The state government also supported the findings of Special Observer Ravi Prasad and the inception report submitted by M/s Intercontinental Consultants & Technocrats Pvt. Ltd. (ICT).
The PWD recommended incorporating their findings into the Detailed Project Reports (DPRs) for the highway projects.
Key recommendations included:
- Underground drainage systems.
- Slope stabilisation along hilly road stretches.
- Improved cross-drainage systems.
- Adequate road camber for proper water runoff.
- Stronger monitoring of construction and maintenance work.
The department further stressed that NHIDCL’s additional field personnel must remain physically present at project sites.
Their responsibility would include supervising work carried out by the alternative maintenance agency, M/s J. Infratech Limited.
NHIDCL’s counsel also received a copy of the state’s observations for necessary action.
NHIDCL Must Submit Report Before November 24 Hearing
After considering the submissions, the High Court directed NHIDCL to examine the state’s concerns and initiate corrective measures without delay.
The agency must submit its pending progress report by November 24, 2026. The court will review the matter again on that date.
Deputy Solicitor General of India Bidyut Majumder, senior advocate Bibhal Nandi Majumder, and advocates Pinki Chakraborty and Rajib Saha appeared for the respondents.
Frequently Asked Questions (FAQs)
Q1. Why did the Tripura High Court issue directions to NHIDCL?
The court noted that NHIDCL had failed to submit its overdue bi-weekly highway progress report despite an earlier order.
Q2. What is the deadline for NHIDCL to submit the report?
The agency must submit the pending report by November 24, 2026.
Q3. Which highway stretch has suffered the most damage?
The PWD identified the Khowai-Srirampur stretch under Package-V, reporting severe damage across more than 64 per cent of the road.
Q4. Which highway projects face repair and construction delays?
The concerns involve Package-II, Package-III, Package-IV and Package-V, covering sections of NH-108B and NH-208.
Q5. When will the High Court hear the case again?
The next hearing is scheduled for November 24, 2026.
National highways play a crucial role in Tripura’s connectivity with other parts of Northeast India. Better road infrastructure is essential for passenger safety, trade, transportation and access to essential services. The High Court’s intervention highlights the importance of timely construction, permanent repairs and accountability in highway development across the state.